News | ![]() |
06.11.2020
BT SVAP COMPLETED WORKS ON THE "ARKTIK LNG-2" PROJECTA set of works has been completed on the territory of IPK SVAP-Center, including acceptance from the Contractor of JSC OMK of steel pipes with a diameter of 159-530 mm, the subsequent application of a protective anti-corrosion coating and shipment of finished piles to the General Customer, used during construction as elements of pile foundations at the ARKTIK LNG-2 facility. Specialized packaging was used during the shipment of finished products to ensure the guaranteed safety of the coating at all stages of multimodal transportation, transshipment and storage. The total supply of piled products with protective coatings to the Arkhangelsk Commercial Sea Port amounted to more than 5,000 tons. The delivery of finished products was carried out in full compliance with the technical requirements of the project according to the agreed schedule. Customer: “ARKTIK LNG-2” LLC |