Project experience | ![]() |

Offshoot pipeline to Nizhneturinskaya hydro-electric power plant
Implementation: |
2014 |
Project owner: |
TGK 9, OAO. Gazprom, PAO |
Contractor: |
Neftegasstroy LLC |
Location: |
Sverdlov region |
Length: |
2 600 м |
The pipe type used in the project: |
Ø426х6 |
Description:
Construction of the offshoot pipeline from the main gas pipelines to Nizhneturinskaya hydro-electric power plant