Project experience

Underwater crossing, the Oka river, sector N 42

Underwater crossing, the Oka river, sector N 42

Implementation: 
2019

Project owner: 
Transneft-TSD, LLC

Contractor: 
VolgaNeftGasStroy

Location: 
Orel region

Length: 
470 m

The pipe type used in the project: 
Ø 530х12 mm

Underwater crossing, the Oka river, sector N 42
Description:


Products: pipes 530 mm with external protection weight concrete coating ZUB of 55 mm thick in a galvanized jacket, protection kit for pipeline weld joints (concrete semi-rings). The use of these products provided reliable protection of the pipeline anticorrosive coating and guaranteed the required ballasting in full compliance with the design solutions. Project implementation period: July-August 2019.