Project experience

Mozdok-Grozny main pipeline

Mozdok-Grozny main pipeline

Implementation: 
2019

Project owner: 
Kirus LLC

Location: 
North Ossetia

Length: 
362 m

The pipe type used in the project: 
Ø 1020х12 мм

Mozdok-Grozny main pipeline
Description:


Casing protection by protective ZUB-COMPOSITE coating during the laying of pipes in complicated pebble gravels by the Direct Pipe method. To provide the cases strength balance the pipe joints caulking was fulfilled by specially developed polyurethane compound of fast curing. The strength of the compound is equal to the strehgth of concrete. The company experts have supplied all the required materials and held in-situ training of the personnel.

Back to the list